Report slams response to nuclear crisis

The operator of the Fukushima nuclear power plant and its regulators all failed in their duty to adequately prepare for and respond promptly to a major emergency, contributing to the worst nuclear accident in a quarter century, according to a committee investigating the disaster.

Tokyo Electric Power, the operator of the Fukushima plant, and its regulators were so unprepared for a major nuclear emergency that they lacked even the basic safety measures to respond to a disaster of the scale that hit Fukushima Daiichi nuclear power plant in the wake of the March 11 tsunami, the committee states in an interim report of its findings.

Tepco’s off-site emergency response headquarters for example, was housed in a building that “was not designed to withstand elevated radiation levels, although it was intended for use in nuclear emergencies”, and did not even have air cleaning filters, it says.

您已阅读39%(895字),剩余61%(1427字)包含更多重要信息,订阅以继续探索完整内容,并享受更多专属服务。
版权声明:本文版权归manbetx20客户端下载 所有,未经允许任何单位或个人不得转载,复制或以任何其他方式使用本文全部或部分,侵权必究。
设置字号×
最小
较小
默认
较大
最大
分享×